A cold recycling train led by Wirtgen's W 380 CRi proved to be just right for a road widening project on a route near Silkeborg, in central Denmark, by rehabilitating and completing the project in just four days.
Using conventional asphalt paving methods, the process would have involved milling off the entire road surface in several stages and then widening and repaving the roadway from the ground up. In contrast, in-place cold recycling used the existing asphalt material on the spot to produce a qualitatively new BSM (bitumen stabilized material) base layer.
The Wirtgen W 380 CRi cold recycler first milled off the existing asphalt pavement to a depth of 15 cm and then added foamed bitumen and cement to the milled material to directly produce the new mix in the machine's milling and mixing chamber. Approximately 300 t of BSM per hour were transferred to the Vögele SUPER 2100-3i road paver following on behind, which then paved the new pavement profile to a width of 5.5 m and a depth of 12 cm in one single pass.
The cold recycling train worked its way forward along the 3 km section of the Sinding Hedevej at a rate of 4 m/min. The road was able to be temporarily reopened for local road users immediately after the Hamm rollers had completed the final compaction.
Material savings plays big role for lower costs
According to lead contractor Arkil A/S, the costs were 30 percent lower than for a conventional rehabilitation project. In view of this, the municipal authorities in Silkeborg are already planning the next road construction project with the cold recycling method.
Savings on materials played the biggest role in the reduction of the overall project costs. Thanks to foamed bitumen technology from Wirtgen, considerably less bitumen needs to be added as a binding agent than would be required to produce new asphalt mix. Hot bitumen was delivered to the site and automatically injected in-place during the milling and mixing process via the Vario injection bar. Thanks to process-dependent machine control, the feed volume was directly matched to the travel speed of the machine and ensured the homogeneity of the mix transferred directly to the SUPER 2100-3i paver.
Another advantage: the final asphalt surface layer can be paved thinner than usual. In this case, only 3 cm of the high-quality surface layer material was used, instead of the usual 4 to 5 cm. This also helped to reduce the overall construction costs.
Sustainability also in mind with cold recycling process
Lower haulage costs led to further cost savings. The recycling area of over 12,000 m2 produced almost 4,000 t of material that did not have to be removed from the site. Two factors played a role in the reduction of CO₂ emissions: the elimination of the movement of a calculated 400 truckloads of material to and from the site and, a considerable reduction of the 3,800 t of fresh hot-mixed-asphalt that would have had to be produced for the base layer in the case of conventional asphalt paving. According to Arkil, these factors enabled an up to 70 percent reduction of the overall CO₂ emissions.
"Essentially, cold recycling is suitable for the rehabilitation of all kinds of roads. It was particularly good here, as no material had to be moved to or from the site and we were also able to widen the roadway as well in a single pass. And that seriously reduces our carbon footprint," emphasizes Mikkel Caprani, Site Manager from Arkil A/S.
Thanks to the clear advantages of cold recycling with foamed bitumen, it has already become established as a standard practice in road construction in many parts of the world. Whether for in-place rehabilitation, as in Silkeborg with a CR-series cold recycler, full-depth recycling (FDR) through and below the base layer with a WR-series wheeled recycler, or decentralized in-plant mixing in a cold recycling asphalt mixing plant such as the KMA 240(i), foamed bitumen technology delivers extremely durable BSM mixes for more sustainable road construction.
What's more, no matter which cold recycling method is chosen and which Wirtgen Group production system is used, a considerable reduction of CO₂ emissions and overall costs for primary resources is consistently guaranteed.
Company info
6030 Dana Way
Antioch, TN
US, 37013
Website:
wirtgen-group.com/en-us
Phone number:
615-501-0600